OPTIMIZATION OF CONSTRUCTION SCHEDULE ON THE CRITERION OF INEQUALITY IN THE DISTRIBUTION OF LABOR FORCES

Authors

  • A. V. Kiyanets South Ural State University, Chelyabinsk, Russian Federation

Keywords:

construction schedule, labor movement diagram, coefficient of inequality in the distribution of labor resources, Gantt chart, construction organization project, manufacturing project, construction project management

Abstract

Being one of the technical and economic indicators of construction schedule, the coefficient of inequality in the distribution of labor forces (coefficient of uneven labor movement) kun reflects the distribution of labor forces over time, is responsible for the optimization and regulation of construc-tion period, is the basis for calculating the number of temporary buildings on a construction site, fol-lowed by the need for space for these buildings at a construction site. The problem resides in the ab-sence in the publicly available sources of substantiated data on the values of this coefficient and regulatory requirements for its limitation and calculation. To solve this problem, a new method for determining the maximum value of kun based on the projected or required duration of the steady-state flow in the flow line manufacturing is proposed. For this, mathematical modelling of multiple variants of labor movement diagrams is carried out while fixing the values of duration and labor in-tensity. This variant modelling makes it possible to obtain the dependence of kun on the steady-state flow time. The mathematical dependence for assigning the limiting kun within the time of the steady-state flow equal to from 25 to 100 % of the total duration of the work is determined, which allows dynamically changing kun depending on the specific conditions for the design of the construction schedule and the general organization and management of the construction project.

References

СП 48.13330.2019 «СНиП 12-01-2004. Ор-ганизация строительства».

Korol, O. Factors affecting the consumption of fuel and energy resources during the construction of monolithic buildings / O. Korol // E 3S Web of Con-ferences: TPACEE-2019. – 2020. – Vol. 164. – № 08020.

Ekindt, V.T. Multicriteria Scheduling – Theory, Models and Algorithms (Second Edition) / V.T. Ekindt, J.-C. Billaut. – Berlin: Springer, 2006. – 577 p.

Lucko, G. Temporal constraints in linear scheduling with singularity functions: Case of calen-darization / G. Lucko // Journal of Computing in Civil Engineering. – 2014. – Vol. 28. – P. 232–243.

Дикман, Л.Г. Организация строительного производства / Л.Г. Дикман. – М.: Изд-во Ассо-циации строительных вузов, 2006. – 626 c.

Кирнев, А.Д. Организация в строительст-ве / А.Д. Кирнев. – 3-е изд., стер. – СПб.: Лань, 2020. – 528 с.

Рыжевская, М.П. Организация строи-тельного производства / М.П. Рыжевская. – Минск: РИПО, 2019. – 308 с.

Олейник, П.П. Организация строительно-го производства: подготовка и производство строительно-монтажных работ / П.П. Олейник, В.И. Бродский. – 2-е изд. – М.: МИСИ – МГСУ, 2020. – 96 с.

Пособие по разработке проектов органи-зации строительства и проектов производства работ для жилищно-гражданского строительст-ва (к СНиП 3.03.01-85)/ ЦНИИОМТП. – М.: Стройиздат, 1989. – 160 с.

Ammar M.A. Optimization of project time-cost trade-off problem with discounted cash flows / M.A. Ammar // Journal of Construction Engineering and Management. – 2011. – Vol. 137 – P. 65–71.

Карякин, А.М. Интерактивная процедура многокритериальной оптимизации при составле-нии календарных планов / А.М. Карякин, В.В. Берез-ка // Вестник ИГЭУ. – 2013.– № 2. – С. 1–4.

Мищенко, В.Я. Оптимизация календарного плана строительного производства путем перерас-пределения нескладируемых ресурсов / В.Я. Мищенко, М.Г. Добросоцких, Е.Э. Эрсбурн // Недвижимость: экономика, управление. – 2019. –№ 1. – С. 83–87.

Reprofiling of transport infrastructure ob-jects with monolithic reinforced concrete frame / D. Topchiy, A. Bolotova, A. Vorobev, A. Atamanenko // IOP Conference Series: Materials Science and Engi-neering. – 2020. – Vol. 918. – № 012025.

Мищенко, В.Я. Оптимизация календар-ного плана строительного производства на основе учета пространственно-технологических связей / В.Я. Мищенко, М.А. Преображенский, М.Г. Добро-соцких // Безопасность критичных инфраструк-тур и территорий. Проблемы безопасности строительных критичных инфраструктур – Safety 2018: сб. ст. – Екатеринбург: НИЦ «НиР БСМ» УрО РАН; УрФУ им. первого Президента России Б.Н. Ельцина, 2018. – С. 164–172.

Малкин, М.М. Оптимизация графиков движения рабочих в календарных планах методом вариации ресурсных профилей: автореф. дис. … канд. техн. наук / М.М. Малкин. – СПб.: Изд-во СПбГАСУ. 2010. – 15 с.

Optimal order of construction of facilities in complex development with minimal additional costs / A. Mailyan, E. Korol, R. Petrosyan, D. Antoniadi // IOP Conference Series: Materials Science and Engi-neering. International Conference on Materials Phys-ics, Building Structures and Technologies in Con-struction, Industrial and Production Engineering, MPCPE 2020. – 2020. – Vol. 896. – № 012052.

Kuzhin M. Optimization of construction pa-rameters using resource scheduling / M. Kuzhin, M. Akimockina // E3S Web of Conferences. – 2019. – Vol. 97. – № 06030.

Anisimov, V. Model and Algorithm for Substantiating Solutions for Organization of High-Rise Construction Project / V. Anisimov, E. Anisimov, A. Chernysh // E3S Web of Conferences: International Scientific Conference on High-Rise Construction, HRC 2017. – 2018. – Vol. 33. – № 030032017.

Pocebneva, I. Models of resource planning during formation of calendar construction plans for erection of high-rise buildings / I. Pocebneva, V. Belousov, I. Fateeva // E3S Web of Conferences:International Scientific Conference on High-Rise Construction, HRC 2017. – 2018. – Vol. 33. – № 030032017.

Formation of optimal performance of works during establishment of the complex of objects optimal sequence of establishing objects complex building / A. Mailyan, G. Afanasiev, D. Antoniadi, R. Petrosyan // IOP Conference Series: Materials Science and Engineering. Building Structures and Technologies in Construction, Industrial and Production

Engineering, MPCPE 2020. – 2020. – Vol. 896. – № 012053.

Lapidus, A. Construction project organiza-tional and technological parameters analysis / A. Lapidus, M. Kuzhin, I. Shesterikova // IOP Confe-rence Series: Materials Science and Engineering. In-ternational Scientific Conference on Advance in Civil Engineering: Construction – The Formation of Living Environment, FORM 2020. – 2020. – Vol. 869. – № 07204723.

Published

2021-09-16