Maximization Problems the Volume of Performed Works in Project Management

Authors

  • S. A. Barkalov Voronezh State Technical University
  • V. N. Burkov V.A. Trapeznikov Institute of Control Sciences of Russian Academy of Sciences
  • A. M. Khodunov Voronezh State Technical University

DOI:

https://doi.org/10.14529/ctcr190206

Keywords:

work value, schedule, work time dependencies, costs, network with orderly works

Abstract

Scheduling tasks (time management) are an important functional area of project management. As a rule, for a given project duration, the tasks of minimizing the amount of required resources, either of the type of costs (cost) or type of capacity (equipment), are considered. Such tasks arise in two cases. In the first case, the duration of the project (program) is strictly limited, but its partial implementation is allowed. In the second case, the project (program) is carried out by periods and the task of maximizing the value (weighted volume) of work performed in each period is set. The paper considers the tasks of forming the calendar work plans of a project (or program projects) by the criterion of maximizing the total weighted volume of work performed, with restrictions on the duration of the project (program) and its cost. In this case, the dependence of the works cost on their duration are given. The cases of independent works, consecutive works, a project consisting of several chains of consecutive works, a project described by a network schedule with ordered events are considered. Examples of solving the problem for different cases are presented.

Author Biographies

S. A. Barkalov, Voronezh State Technical University

д-р техн. наук, заведующий кафедрой управления строительством

V. N. Burkov, V.A. Trapeznikov Institute of Control Sciences of Russian Academy of Sciences

д-р техн. наук, профессор, заведующий лабораторией активных систем

A. M. Khodunov, Voronezh State Technical University

аспирант кафедры управления строительством

References

Математические основы управления проектами: учеб. пособие / С.А. Баркалов, В.И. Воропаев, Г.И. Секлетова и др.; под ред. В.Н. Буркова. – М.: Высшая школа, 2005. – 421 с.

Сетевые модели и задачи управления / В.Н. Бурков, Б.Д. Ланда, С.Е. Ловецкий и др. – М.: Советское радио, 1967. – 144 с.

Баркалов, С.А. Задачи календарного планирования работ с переменными объемами / С.А. Баркалов, В.Н. Бурков, А.М. Ходунов // Экономика и менеджмент систем управления. – 2018. – № 4 (30). – С. 76–83.

Буркова, И.В. Метод сетевого программирования в задаче целочисленного линейного программирования / И.В. Буркова, А.Р. Кашенков // Теория активных систем – 2011. Труды международной научно-практической конференции. – М.: Институт проблем управления РАН, 2011. – С. 25–26.

Буркова, И.В. Метод сетевого программирования в задачах нелинейной оптимизации / И.В. Буркова // Автоматика и телемеханика. – 2009. – № 10. – С. 15–21.

Published

2019-05-26

Issue

Section

Control in Social and Economic Systems